Schedule

2017

  • Environmental Assessment Completed and FONSI Acquired (Finding of No Significant Impact)

2018

  • Winter: Project Team Established and Public Involvement Begins for Next Phase (Elected Officials Briefing (EO), Community Advisory Group Meeting (CAG), Public Meetings Held)
  • Summer: Missouri Highways and Transportation Commission Approves Project for Design-Build

2019

  • Spring: Project Advertised to Contractors and Public Meetings Held (March: Project Advertised / April: Request for Qualifications released - CAG, EO, & Public Meetings held)
  • Summer: Project Goes Out to Contractors for Bidding (June: Request for Proposals released - Between 2-5 Design-Build teams shortlisted)
  • Fall: Design-Build Contract Awarded in November

2020

  • Construction Begins

2023

  • Construction Complete by December