Detour Information

2022 Closures

Aug 2021

  • Pershall Road Lane Closure Elizabeth to Old Halls Ferry Closure Duration: 9 Months (Continuation of 2021 Work)

Nov 2021

  • Dunn Road Lane Closure Old Halls Ferry to West Florissant Closure Duration: 3 months (Continuation of 2021 Work)

Feb 2022

  • New Florissant Closed at 270 - Bridge Demo (East Bound) Closure Duration: 1 Weekend

March 2022

  • North and South Bound New Florissant Lane Closures Closure Duration: 2 Weeks

May 2022

  • Pershall Road Lane Closure Hanley to New Florissant Closure Duration: 4 Months

Jul 2022

  • South Bound 67 at Southern Tie-in to Existing South Bound 67 Closure Duration: 1 Weekend
  • East Bound 270 to North Bound/South Bound 67 Ramp Closed Closure Duration: 1 Week
  • South Bound 67 to West Bound 270 Ramp Closed Closure Duration: 3 Weeks
  • Taylor to South Bound 67 Closed Closure Duration: 3 Weeks

Aug 2022

  • East Bound 270 On Ramp from Hanley/Graham Closed Closure Duration: 2 Months
  • Dunn Road Closed at Taylor Closure Duration: 3 Weeks
  • New Halls Ferry Closed at 270 - Bridge Demo (East Bound) Closure Duration: 1 Weekend
  • South Bound 67 Closed at Taylor - 67 Traffic Detoured thru Taylor Closure Duration: 1 Month
  • East Bound 270 Exit Ramp to West Florissant Closed Closure Duration: 2 Months
  • East Bound 270 On Ramp from Washington/Elizabeth Closed Closure Duration: up to 3 Months

Sep 2022

  • East Bound 270 Exit to New Florissant Closed Closure Duration: 1.5 Months
  • West Bound 270 On Ramp from New Halls Ferry Closed Closure Duration: 3 Months
  • New Florissant Closed at 270 - Bridge Demo (West Bound) Closure Duration: 1 Weekend

Oct2022

  • East Bound 270 Exit Ramp to New Halls Ferry Closed Closure Duration: 2 Weeks

Nov 2022

  • Dunn Road Closed between Lynn Haven and 637 Dunn Road Closure Duration: 1 Month

Dec 2022

  • East Bound Dunn Road Closed Coldwater Creek to Graham Closure Duration: 2 Months
  • West Bound 270 On Ramp from Hanley/Graham Closed via Dunn Road Closed Closure Duration: 1 Week
  • Dunn Road Lane Closure West Florissant to Washington Closure Duration: 3 Months
  • West Bound 270 On Ramp from West Florissant Closed Closure Duration: 1 Month
  • East Bound Dunn Road Closed Coldwater Creek to Graham Closure Duration: 2 Months

July 2023

  • West Bound 270 to North Bound 367 Ramp Closed Closure Duration: 2 Months

Project team:

Missouri Department of Transportation I‑270 Project Millstone Weber Parsons

This schedule is subject to change.