Milestones & Project Goals
Milestones
End of March 2019
- Design Build Procurement Begins
November 2019
- Project Advertisement March 2019
- Request for Qualifications is released in April 2019
- Shortlist between 2-5 Design Build teams in June 2019
- Request for Proposals is released in June 2019
February 2020
- Construction Begins
December 2023
- Construction Complete
Project Goals
- Deliver the project by December 1, 2023 within the program budget of $225 million.
- Maximize reliability and safety while linking communities for all users.
- Provide a durable and maintainable transportation network making Interstate 270 the conduit for a prosperous region.
- Grow and utilize a diverse workforce.
- Minimize and mitigate impacts to customers through innovation.