Milestones & Project Goals

Milestones

End of March 2019

  • Design Build Procurement Begins

November 2019

  • Project Advertisement March 2019
  • Request for Qualifications is released in April 2019
  • Shortlist between 2-5 Design Build teams in June 2019
  • Request for Proposals is released in June 2019

February 2020

  • Construction Begins

December 2023

  • Construction Complete

Project Goals

  1. Deliver the project by December 1, 2023 within the program budget of $225 million.
  2. Maximize reliability and safety while linking communities for all users.
  3. Provide a durable and maintainable transportation network making Interstate 270 the conduit for a prosperous region.
  4. Grow and utilize a diverse workforce.
  5. Minimize and mitigate impacts to customers through innovation.