Project Schedule
Pre-Construction Schedule
2017
- Environmental Assessment Completed and FONSI Acquired (Finding of No Significant Impact)
2018
- Winter: Project Team Established and Public Involvement Begins for Next Phase (Elected Officials Briefing (EO), Community Advisory Group Meeting (CAG), Public Meetings Held)
- Summer: Missouri Highways and Transportation Commission Approves Project for Design-Build
2019
- Spring: Project Advertised to Contractors and Public Meetings Held (March: Project Advertised / April: Request for Qualifications released - CAG, EO, & Public Meetings held)
- Summer: Project Goes Out to Contractors for Bidding (June: Request for Proposals released - Between 2-5 Design-Build teams shortlisted)
- Fall: Design-Build Contract Awarded in November
Construction Schedule
2020
The following locations are scheduled to begin construction activities in 2020.
- Pershall construction between New Florissant and Washington/Elizabeth
- Old Halls Ferry Bridge and Interchange
- Washington/Elizabeth Bridge and Interchange
- US 67 (Lindbergh) Interchange construction begins (Duration of 2.5 years)
- Bellefontaine Interchange
- Southbound I-170 Widening
- Pershall Bridge connection to Dunn over I-270 east of Old Halls Ferry
2021
The following locations are scheduled to begin or continue construction activities throughout 2021.
- Coldwater Creek Bridges
- West Florissant Bridge and Intersection
- Outer Road Improvements begin
- MO 367 Interchange construction begins
- Pershall Bridge connection to Dunn over I-270 east of Old Halls Ferry
- US 67 (Lindbergh) Interchange construction continues
2022
The following locations are scheduled to begin or continue construction activities throughout 2022.
- Mainline I-270 Widening begins
- I-270 Over New Halls Ferry EB Bridge
- I-270 Over New Florissant EB Bridge
- MO 367 Interchange construction continues
- US 67 (Lindbergh) Interchange construction continues
2023
The following locations are scheduled to wrap up construction activities in 2023.
- Mainline I-270 Widening continues
- I-270 Over New Halls Ferry WB Bridge
- I-270 Over New Florissant WB Bridge
- Mainline I-270 Asphalt Overlay
- MO 367 Interchange construction completed
- US 67 (Lindbergh) Interchange construction completed
- Project Completed December 2023